Regional authority halts Belgian Google data center construction

Regional authority halts Belgian Google data center construction

For the time being, the Walloon town of Farciennes will not be getting a Google data center. Although the construction permit had already been revoked this summer, Google continued building. Now, the Walloon Region has forced a halt to the project.

According to Raphael Stokis, a senior official with the Walloon Region, there were about 300 construction workers on site when the project was halted. Walloon Minister of Infrastructure François Desquesnes announced an investigation on Wednesday, and two days later, the halt became official.

Greenpeace sounded the alarm earlier this week. According to the environmental organization, satellite images show that work had continued over the past few months. Greenpeace subsequently initiated an emergency proceeding. “This shows a lack of respect for the environment, local residents, and the law,” the organization states.

From air cooling to Sambre river water

The dispute centers on a change to the project that rendered the permit invalid. Google wanted to expand the data center and switch from air cooling to cooling using water from the Samber River. The amended permit allowed for up to 600 cubic meters of river water per hour. Desquesnes revoked that permit in August, following objections from local residents and concerns about drought. In October, Google appealed to the Council of State to allow the project to proceed with the modification.

In the meantime, the company continued working on the roof, among other things. Google maintains that the original permit for an air-cooled data center is still valid. The Walloon government disagrees: in its view, the project involves elements covered by the revoked permit.

Expansion in Hainaut

Farciennes is located near Charleroi. The project is part of Google’s expansion plans in the province of Hainaut, where the company intends to build three new data centers. Energy neutrality is a requirement there. Google announced the project as an investment of approximately 1 billion euros. The company has been active in the region for quite some time. In Saint-Ghislain, about a half-hour drive from Farciennes, a large Google campus is already in operation.

Google itself has responded cautiously to the suspension. Through a spokesperson, the company stated that it is committed “to an open and collaborative dialogue with the regional government and experts regarding investments in Wallonia.” It is not yet known when the Council of State will issue its ruling.